A positive expert opinion was received on the projects of the deep oil refining complex at NZNP

04 October 2019
Examination of project documentation and engineering survey results was carried out in relation to all technological facilities of the complex, including off-site facilities:
- unit for hydrotreatment of kerosene, diesel fuel with a capacity of 2,160.8 thousand tons/year;
- combined hydrocracking unit with a capacity of 2,571 thousand tons/year with a hydrogen production section with a capacity of 70 thousand tons/year;
- installation of sulfur production of the 2nd stage with a capacity of 95 thousand tons/year;
- delayed coking plant with a capacity of 1,860 thousand tons/year.
Currently, the kerosene and diesel fuel hydrotreatment unit is at the stage of developing working documentation, and the working and design documentation for the main process equipment is being actively reviewed.